Franklin County Engineer Facebook Feed

Franklin County Engineer

As a local public works agency headquartered in Columbus, Ohio, the Franklin County Engineer's Office is responsible for the maintenance and construction of 271 miles of county roadway and 351 county bridges, as well as upkeep of all county ditches, drains, retention basins, and other storm water facilities within the right-of-way of county roads in unincorporated areas. To meet the continuing development and infrastructure needs of Franklin County, the Engineer's Office utilizes the latest technologies for determining and maintaining roadway centerlines and boundaries; retracing and setting new monuments for original public land surveys; preparing geographic information system mapping for real estate tax assessments; and establishing precise countywide horizontal and vertical control to maintain uniformity in construction, surveying, and mapping.
Franklin County Engineer
Franklin County Engineer
Beach Road, between Amity Road and Plain City-Georgesville Road, will be closed beginning Monday, August 31, 2026, for bridge rehabilitation work. The closure will last approximately five (5) days, weather permitting.
Franklin County Engineer
Franklin County Engineer
Cooke Road improvements are moving forward! Crews are making progress on storm sewer, roadway construction and new curb and gutter from Karl Road to Cleveland Avenue. Beginning Sept. 14, one westbound lane will reopen between Karl Road and Dresden Street, weather permitting.
Franklin County Engineer
Franklin County Engineer
Notice to Contractors: We are accepting bids on the Kropp Road Drainage Outlet Improvement Part 2 Improvements Project. Visit: https://www.bidexpress.com/solicitations for more information.
Franklin County Engineer
Franklin County Engineer
Cooke Road, between Dresden Street and Walford Street, is closed for roadway improvements and the addition of pedestrian facilities. The closure will last approximately seventy-five (75) days, weather permitting.
Franklin County Engineer
Franklin County Engineer
We had a fantastic time at New Albany’s Touch-A-Truck event! Families stopped by to explore our snowplow truck, get a closer look at the equipment we use to keep our roadways safe, and pick up some fun giveaways. The day was filled with lots of excitement, curious kids, and wonderful conversations with the community. Thank you to the New Albany, Ohio Government for hosting such a fun and engaging event!
Franklin County Engineer
Franklin County Engineer
Hardy Parkway Street, south of Frank Road, is now closed for roadway improvements. The road is expected to remain closed for approximately 30 days, weather permitting.
Franklin County Engineer's Office
970 DUBLIN ROAD
COLUMBUS, OHIO 43215
(614) 525-3030
fracoeng@franklincountyengineer.org

Follow Us

Top
 

Bridge Builders Biography Chapter 12

Bridge Builders Biography Chapter 12

Beach Road Cable-Stayed Bridge

bridge
bridge

Despite the practicality of cable-stayed technology developed in France and Great Britain during the 1800s, this style of bridge would not be widely built until after World War II when French Engineer Albert Caquot (1881-1976) and German Engineer Franz Dischinger (1887-1953) introduced effective and economical cable-stayed bridge designs in answer to major steel shortages in Europe.

The first cable-stayed suspension bridge entirely located in Ohio was built by the the C.J. Mahan Construction Company in 2001 for $3 million. It carries Beach Road over the Big Darby Creek in Brown Township.

The 300-foot long structure, designed by Jones-Stuckey Ltd, Inc. is supported by cables connected to four 80-foot tall towers.

To protect the environmentally sensitive area, the single span bridge was configured without any piers in the waterway.